  • Dr. B.R.Ambedkar Pranahitha-Chevella Sujala Sravanthi-Lift Irrigation Scheme, Telangana


    Pranahitha-Chevella LIS

    The Pranhita-Chevella Sujala Sravanthi lift irrigation scheme is proposed to be implemented over a span of 4 years at an investment of Rs. 38,500 crore. The scheme is contemplated to provide irrigation facilities for an ayacut of 1.64 million acre and drinking water enroute to Adilabad, Karimnagar, Nizamabad, Medak, Nalgonda, Rangareddy and Warangal districts.
    The estimated completion time of the project being 48 months, will bring in 30 tmc drinking water to Hyderabad along with 16 tmc for industrial purposes from River Godavari.
    The scope of work under package-5 includes Execution of Pumping station, Supply, Erection of pumps and motors, Laying pressure mains, Construction of delivery cistern and Excavation of gravity canals, including formation of  embankments, Construction of sluices, CD & CM works, Excavation of 17.5 Kms. long Tunnel, construction of Barrage across Rallavagu and Lining  etc., complete for the reach from Km 71.50 to Km 116.00 (Up to Sripada Yellampally Project) which is taking off from the right flank of the proposed  Barrage across  River Pranahita near Tummidi Hetti (V) Kouthala (M) Adilabad District.
    The design engineering work under package V was carried out by ConTec for M/s Megha Engineering & Infrastructures Ltd. for the EPC group, M/s MEIL - MAYTAS - ABB - ANDRITZ (JV).